Posted on July 9, 2026 at 7:28 AM by John Guccione
Beginning on Thursday, July 9 at around 10:30 a.m., the contractor will remove the top 3 inches of the existing pavement on Oakley Avenue. This work will be completed using a large pavement grinding machine.
Paving is scheduled to begin on Friday, July 10th at approximately 7:30 a.m. This 1 inch lift of “leveling” pavement mix is placed with the objective to fill in voids and provide a better end product.
The final lift of surface mix will be placed in 1-2 weeks after subsurface structure adjustments have been completed. Additional notice will proceed the final paving operation.
Please note the following important access and parking restrictions:
- LIMITED ACCESS DURING PAVEMENT REMOVAL OPERATIONS ON THURSDAY
- NO ACCESS DURING DAYTIME PAVING OPERATIONS ON FRIDAY
- NO PARKING ON THE ROADWAY DURING PAVEMENT REMOVAL OR PAVING OPERATIONS