2025 Hazel Avenue Reconstruction Project

Subscribe to receive updates on the 2025 Hazel Avenue Reconstruction Project.

View All Posts

Oct 03

Hazel Project Update - 10/3/2025

Posted on October 3, 2025 at 3:09 PM by Tyler Dickinson

This week, the contractor’s underground crew began installing new water service lines between the bridge and Chestnut Street. This work is scheduled to continue into next week.

Meanwhile, the contractor continued pouring new curbs and sidewalks between the bridge and Wayne Avenue. This concrete work is expected to be completed next week, allowing for the first layer of asphalt paving in that section to take place by the end of the week.

We appreciate your continued patience and support as we improve Deerfield’s infrastructure. If you have any questions, please contact the Village of Deerfield Engineering Department at 847-317-2490 and ask about the Hazel Avenue Infrastructure Project.