View All Posts

May 04

Project Update – May 4, 2026

Posted on May 4, 2026 at 7:17 AM by John Guccione

PAST WEEK ACCOMPLISHMENTS:  Pavement removal is 50% completed on Linden/Berkely. 

ACTIVE LOCATION SUMMARY: 

Berkley Court & Linden Ave:   Pavement removal will continue this week on Berkley Court.  Curb placement will take place the week of 5/4/26 (additional notification will follow).

Broadmoor Place & Somerset Ave:   Underground work is will begin on Monday, May 4th.