Hazel Project Update - 3/21/2025

Posted on March 21, 2025 at 2:49 PM by Tyler Dickinson

Construction Update – 3/21/2025

This week, necessary tree protection fencing for preserved trees and construction signage have all been completed along Hazel Avenue.

Looking ahead to next week, the contractor will continue installing the new utilities between Wilmot Road and Appletree Road, while the second crew will continue working on the storm sewer installation near Broadmoor Place, working eastward.

Due to the size and locations of the pipes being installed, non-local traffic will be detoured. Motorists who do not live along this section of Hazel Avenue are encouraged to use alternate routes, such as Deerfield Road or Greenwood Road, to avoid the construction area.

Additionally, next week, ComEd will continue relocating their utility poles along Hazel Avenue, which may require temporary power interruptions. Affected properties will receive advance notifications from ComEd's notification system. Residents are encouraged to ensure ComEd has their up-to-date contact information for these alerts.

Please note, the information provided is a forecast of the proposed operations and may change due to contractor availability or weather conditions.

The Village appreciates your cooperation in supporting this project and thanks you for your patience. If you have any questions, please contact the Village of Deerfield Engineering Department at 847-317-2490 and ask to speak with someone about the Hazel Avenue Infrastructure Project.