The original item was published from May 13, 2024 8:59 AM to May 13, 2024 10:02 AM
The below forecast provides a weekly preview of construction operations per location. All tentative schedules shown below are weather dependent.
-----------
Area: A Country Lane, Arthur Court, Merlin Court & Edgewood Court PAUSED
Base paving has been completed. Surface paving will take place in the next 4-6 weeks.
Area: B Gordon Terrace, Burning Tree Lane & Maya Court ACTIVE
Concrete road removals will begin in the next 1-2 weeks. Additional notification will be distributed prior to beginning these operations.
Area: C Burr Oak & Rosewood ACTIVE
Concrete patching on Burr Oak has been completed. Concrete road removals on Rosewood Ave will begin in the next 1-2 weeks. Additional notification will be distributed prior to beginning these operations.
Area: E Mallard Lane PAUSED
Base paving has been completed. Surface paving will take place in the next 4-6 weeks.
Area: E Orchard Street, Caroline Court & Todd Court COMPLETED
Surface paving has been completed. Minor punch list items remain at this location.
Area: F Millstone Road, Smoketree Road, Fox Hunt Trail & Shag Bark Lane ACTIVE
Pavement removal is planned to begin on Tuesday May 14th on Shagbark and Foxhunt, then over to Smoke Tree and Milestone. Residents have been notified using physical notifications that provide additional details. Paving is planned to take place in the next 1-2 weeks.
Area: G Colony ACTIVE
Pavement removals are planned for the end of the week of May 13. Residents have been notified using physical notifications that provide additional details. Paving is planned to take place in the next 1-2 weeks.