[ARCHIVED] Construction Forecast Week of June 3

The original item was published from June 3, 2024 7:16 AM to June 3, 2024 7:33 AM

The below forecast provides a weekly preview of construction operations per location. All tentative schedules shown below are weather dependent. 

-----------

Area: A   Country Lane, Arthur Court, Merlin Court & Edgewood Court  COMPLETED

Area: B   Gordon Terrace, Burning Tree Lane & Maya Court  ACTIVE

Paving base layer of roadway today on Burning Tree Ln and Gordon Terrace. Physical notices were distributed to impacted residents last week with additional details.

Area: C   Burr Oak & Rosewood  ACTIVE

Potential surface paving later today, depending on how efficient paving goes in Area B. Physical notices were distributed to impacted residents last week with additional details.

Area:   Mallard Lane COMPLETED

Area: E  Orchard Street, Caroline Court & Todd Court    COMPLETED

Area: F  Millstone Road, Smoketree Road, Fox Hunt Trail & Shag Bark Lane    COMPLETED

Area: G  Colony Lane COMPLETED

May 13

[ARCHIVED] Construction Forecast Week of May 13

The original item was published from May 13, 2024 8:59 AM to May 13, 2024 10:02 AM

The below forecast provides a weekly preview of construction operations per location. All tentative schedules shown below are weather dependent. 

-----------

Area: A   Country Lane, Arthur Court, Merlin Court & Edgewood Court  PAUSED 

Base paving has been completed.  Surface paving will take place in the next 4-6 weeks.

Area: B   Gordon Terrace, Burning Tree Lane & Maya Court  ACTIVE

Concrete road removals will begin in the next 1-2 weeks. Additional notification will be distributed prior to beginning these operations. 

Area: C   Burr Oak & Rosewood  ACTIVE

Concrete patching on Burr Oak has been completed. Concrete road removals on Rosewood Ave will begin in the next 1-2 weeks. Additional notification will be distributed prior to beginning these operations. 

Area:   Mallard Lane  PAUSED 

Base paving has been completed.  Surface paving will take place in the next 4-6 weeks.

Area: E  Orchard Street, Caroline Court & Todd Court    COMPLETED

Surface paving has been completed.  Minor punch list items remain at this location.

Area: F  Millstone Road, Smoketree Road, Fox Hunt Trail & Shag Bark Lane    ACTIVE

Pavement removal is planned to begin on Tuesday May 14th on Shagbark and Foxhunt, then over to Smoke Tree and Milestone.  Residents have been notified using physical notifications that provide additional details. Paving is planned to take place in the next 1-2 weeks.

Area: G  Colony  ACTIVE 

Pavement removals are planned for the end of the week of May 13. Residents have been notified using physical notifications that provide additional details. Paving is planned to take place in the next 1-2 weeks.

May 13

[ARCHIVED] Construction Forecast Week of May 13

The original item was published from May 13, 2024 8:59 AM to May 13, 2024 10:00 AM

The below forecast provides a weekly preview of construction operations per location. All tentative schedules shown below are weather dependent. 

-----------

Area: A   Country Lane, Arthur Court, Merlin Court & Edgewood Court  PAUSED 

Base paving has been completed.  Surface paving will take place in the next 4-6 weeks.

Area: B   Gordon Terrace, Burning Tree Lane & Maya Court  ACTIVE

Concrete road removals will begin in the next 1-2 weeks. Additional notification will be distributed prior to beginning these operations. 

Area: C   Burr Oak & Rosewood  COMPLETED

Area:   Mallard Lane  PAUSED 

Base paving has been completed.  Surface paving will take place in the next 4-6 weeks.

Area: E  Orchard Street, Caroline Court & Todd Court    COMPLETED

Surface paving has been completed.  Minor punch list items remain at this location.

Area: F  Millstone Road, Smoketree Road, Fox Hunt Trail & Shag Bark Lane    ACTIVE

Pavement removal is planned to begin on Tuesday May 14th on Shagbark and Foxhunt, then over to Smoke Tree and Milestone.  Residents have been notified using physical notifications that provide additional details. Paving is planned to take place in the next 1-2 weeks.

Area: G  Colony  ACTIVE 

Pavement removals are planned for the end of the week of May 13. Residents have been notified using physical notifications that provide additional details. Paving is planned to take place in the next 1-2 weeks.