Blog module icon

All Blog


Find out what's happening in the blog. Below is a list of blog items.

Sep 15

Brierhill Construction Update - 9/15/2017

Posted to 2017 Brierhill Rd Project by Tyler Dickinson

Deerfield Logo small

Village of Deerfield

Brierhill Road Project Construction Update – 9/15/2017

 

THIS WEEK 

The contractor completed the installation of sod, seed, and mailboxes this week. Now that all of the mailboxes are completed, the temporary mailboxes will be removed and regular mail delivery will resume starting Monday. Please ensure all mail has been retrieved from the temporary mailboxes before Monday.

As the sod is new and fragile, please instruct any landscapers/contractors/guests that may be parking on Brierhill Rd to not drive on any of the grass. The sod is still very soft and any vehicles driving on it will result in large ruts in the parkway.


NEXT WEEK

Next week, the contractor will wrap up the remaining miscellaneous items for this project and prep the roadway for final paving. This will include the installation of the new street signs early in the week.

Due to the contractor’s availability as well as to avoid disruptions during Rosh Hashanah, the contractor will not be paving next week as previously communicated. Instead, the contractor is looking to pave the following week and additional communication will be sent out once a date has been set. With the exception of roadway striping, this is anticipated to be the final item completed on this project.

Finally, as the sodding and parkway restoration has been completed, landscapers are invited to resume their normal schedules. This project was difficult enough as it was and the Village would like to thank all of you for cooperating with our original request.


  

Please be advised that the information communicated here is a forecast of proposed operations, which may change due to contractor availability and/or weather conditions.

Jun 23

Construction Forecast for the week of 6/26/2017

Posted to 2017 Street Rehab Project by John Guccione

This construction forecast is for the week of June 26, 2017.

Garand Drive 
Underground sewer repairs and concrete curb and sidewalk installation has been completed on Garand Drive. Pavement removal could begin towards the middle of next week (weather permitting). Additional notice will follow prior to pavement removal. As pavement removal operations could present delayed access to residential driveways.

Wincanton Drive
Construction layout and utility locates have been completed in preparation for the upcoming construction project. Underground sewer work could begin as early as July 5th.

Pine Street
Sod placement is complete. The only remaining work at this location is the placement of asphalt surface pavement, which will take place in the next two months. 

Fair Oaks Avenue
Sod placement is complete. The only remaining work at this location is the placement of asphalt surface pavement, which will take place in the next two months. 

Continue Reading...