Blog module icon

All Blog


Find out what's happening in the blog. Below is a list of blog items.

Jul 21

Brierhill Construction Update - 7/21/2017

Posted to 2017 Brierhill Rd Project by Tyler Dickinson

Deerfield Logo small

Village of Deerfield

Brierhill Road Project Construction Update – 7/21/2017

LAST WEEK

The contractor has completed the pavement removals and excavation this week. They also continued the curb & gutter installation.

SCHEDULE

Curb

The contractor will continue to install curbs next week along Brierhill Rd which will impact driveways at times. As previously talked about, the impacts to driveways may require coordination amongst neighbors as parking in neighboring driveways may be needed. Outside of construction hours, parking in front of homes will be permissible. Notifications with additional information will be delivered to residents prior to driveway impacts.

Paving

In the next 2-3 weeks, the contractor will be ready to pave the roadway. However, due to the width constraints of the roadway and curbs, traffic will be unable to pass the paving operations during the paving of Brierhill Rd. Therefore, the Village has authorized the contractor to pave at night. This will begin on the south end at around 9pm and will be completed by 4 – 5am. This will help limit any impacts to the daytime motorists. The Village will be working with the contractor to give as much advance warning to all residents as possible prior to the paving.





THANK YOU FOR YOUR CONTINUED PATIENCE.

 

 Please be advised that the information communicated here is a forecast of proposed operations, which may change due to contractor availability and/or weather conditions.


Jun 23

Construction Forecast for the week of 6/26/2017

Posted to 2017 Street Rehab Project by John Guccione

This construction forecast is for the week of June 26, 2017.

Garand Drive 
Underground sewer repairs and concrete curb and sidewalk installation has been completed on Garand Drive. Pavement removal could begin towards the middle of next week (weather permitting). Additional notice will follow prior to pavement removal. As pavement removal operations could present delayed access to residential driveways.

Wincanton Drive
Construction layout and utility locates have been completed in preparation for the upcoming construction project. Underground sewer work could begin as early as July 5th.

Pine Street
Sod placement is complete. The only remaining work at this location is the placement of asphalt surface pavement, which will take place in the next two months. 

Fair Oaks Avenue
Sod placement is complete. The only remaining work at this location is the placement of asphalt surface pavement, which will take place in the next two months. 

Continue Reading...