Blog module icon

All Blog


Find out what's happening in the blog. Below is a list of blog items.

May 30

Brierhill Rd Restoration - 5/30/18

Posted to 2017 Brierhill Rd Project by Tyler Dickinson

Deerfield Logo small

Village of Deerfield

Brierhill Road Project Restoration

Brierhill Rd Residents,


The contractor will be returning this spring to replace sod or reseed any parkway areas that did not take or survive the winter. Once these locations have been replaced/reseeded, we ask that residents help out by watering any new sod/seed daily for the first two weeks. While onsite, the contractor will also be performing other miscellaneous tasks to correct any deficient works items related to last year’s construction project. Timing of this work has not been established but this work should take place before July.


Oct 12

Paving on Wincanton, East Canton & West Canton Court Tomorrow.

Posted to 2017 Street Rehab Project by John Guccione

This is a courtesy notice to inform you that surface paving will take place tomorrow, October 13, 2017 on Wincanton, East Canton & West Canton Court.  Paving operations will begin at 7 am and should be completed by 4 pm.

In efforts to achieve optimal smoothness, we ask that you refrain from traveling over the fresh pavement. Therefore, we ask that vehicles be relocated prior to paving operations.

Once paving and compaction is completed, residents will have full access to their driveways 30-40 minutes after compaction (rolling) of asphalt mix.

During paving operations, please note that homeowners will have access to their property at all times via the new sidewalk. However, due to limited space during daytime operations, access to driveways may be delayed or denied at times. Please allow ample time for relocation of vehicles and temporary delays that may occur. Though driveway access may be denied during paving operations, access will be re-established at the end of daytime operations.

The Village appreciates your effort in helping to complete this improvement. If you have any questions or need additional information, please contact the Village of Deerfield Engineering Department at 847-317-2490 and request to speak with someone regarding the Project.

Overnight parking on adjacent streets will be permitted during this phase of construction. The Village of Deerfield Police Department has been notified that residents within this area will be parking overnight on Village streets. During the day, between 7:00 AM and 7:00 PM, please park your vehicle(s) away from the construction area to allow the contractor complete access to the job site. 

Jun 15

Paving Monday on Somerset & Osterman, Plus Location Updates

Posted to 2018 Street Rehab Project by John Guccione

Somerset and Osterman Update
Paving of surface course will take place on Monday June 18th. Fresh oil will be placed early on Monday morning. Please drive slowly to avoid oil splashing on cars.  Somerset will be closed during paving. Osterman will remain open during paving and traffic will be managed by flaggers. The contractor’s flaggers will alternate access to east and west bound traffic allowing passage within 5-7 minutes. This paving operation will result in delays to the motoring public. Please be patient. 

Oxford Update
Asphalt base course paving completed. Next week the contractor will focus on parkway restoration. Final surface will not be placed on Oxford until later in this season. Delaying surface paving will allow any potential settling of utility trenches to occur before placing surface course. This will result in a smoother driving surface. 

Update for Byron Court, Crabtree, Elmwood and Meadow
Work on Byron Court, Crabtree, Elmwood and Meadow is on hold, awaiting availability of underground crews.