Construction Update for week of August 16

Posted on August 16, 2021 at 2:51 PM by Tyler Dickinson

Ambleside, Dimmeydale, and Windcrest
Directional boring for street light conduit began today and weather depending, is expected to be completed by the end of the week. Next week, the contractor will be paving the final surface course. Additional notification will be distributed once the final paving schedule has been determined.
 
Greenwood Avenue
With the completion of the final surface paving last Friday, this location has been substantially completed. The remaining parkway restoration and site cleanup will be completed as weather allows. 
 
Elder Lane
Last week, the contractor completed the curb installation on the north side of the road. Today, the contractor is working to install the curb on the south side of the road as well as the remaining driveway apron and sidewalk locations. Later this week, the contractor will begin pavement removals. Additional notifications will be distributed prior to the start of this work.