Ambleside, Dimmeydale, and Windcrest
This week, the contractor completed the pavement removals throughout the area. For the remainder of the week, the contractor will continue to prepare the roadway base for paving the first layer of asphalt early next week. Additional notification will be delivered later this week once next week's paving schedule is confirmed.
Greenwood Avenue
The contractor completed the remaining underground items this week and started the pavement removals today. The contractor anticipates completing the required pavement removals by the end of this week which will allow the new concrete curb to be installed early next week.
The pavement removals and subsequent curb installation will require vehicles to park offsite while this work is taking place. The Village appreciates the cooperation during this time.
Elder Lane
As discussed in the preconstruction meeting, this roadway will be receiving a new curb as part of the project. The contractor anticipates beginning the first round of curb removal and replacements in the next 1-2 weeks.
Reminder that trash collection at all locations has been rescheduled for early pickup, starting at 6:30am. This is in an effort to avoid any conflicts with the construction crews.