The below summary, is a forecast of construction operations planned for this week.

Ambleside, Dimmydale & Windcrest
JULIE locates will take place this week, as will the delivery of construction equipment and materials. Underground work will begin this Friday, May 14th. Saw cutting will take place mid-week, in preparation for underground work later this week.  This work includes storm sewer work as it relates to roadway drainage and some water main repairs. Most of the construction will be performed in the roadway area except for the replacement of storm sewer structures and/or fire hydrants within the parkway area. Please drive slowly and carefully within construction limits.

Elder Lane(Waukegan to east Limits)
We are still awaiting a schedule from the contractor on this location. However, work should begin in this area in mid-June or early-July.

Greenwood (Waukegan to east Limits)
We are still awaiting a schedule from the contractor on this location. However, work should begin in this area in early to mid-July.