2019 Woodland Watermain Project

Click here to view the complete project details including scope and locations.

Sep 16

Woodland WM Project Update - September 16

Posted on September 16, 2019 at 8:41 AM by Tyler Dickinson

September 16, 2019


Work Completed Last Week:

The underground contractor continued the installation of fire hydrants, water valves, and private water service connections last week. They were also able to complete 3 water main connections to the existing water mains in the area which required water main shutdowns to those properties within the area.

Anticipated Schedule for This Week:

The underground contractor will complete the new water service connections on Hawthorne Ln. on Monday, thereby completing all of the private connections to the new main. The contractor will also be connecting the new water main to the existing main at Hawthorne Ln./North Ave. on Wednesday which will require a full water shutdown for those in the area.

The contractor is expected to be substantially complete with this project by the end of the week. Once this project has been completed, the street rehabilitation project will begin. This project will repair impacted curbs, perform roadway patches, and resurface the roads within the subdivision. In order to receive updates for this upcoming work, residents are encouraged to sign up for the 2019 Street Rehabilitation Project Blog via the Village Website. 

Percentage Complete: 75%

Neighborhood Impacts:

Construction operations will necessitate daily lane closures during working hours which may result in delays to local vehicular traffic. Caution shall be practiced through the construction work zone, and the Village asks that residents be alert for workers and construction equipment.

The Village appreciates your patience while we complete this improvement. If you have any questions or need additional information, please contact the Village of Deerfield Engineering Department at 847-317-2490.

Please be advised that the information communicated here is a forecast of proposed operations which may change due to contractor availability and/or weather conditions.



Sep 09

Woodland WM Project Update - September 9

Posted on September 9, 2019 at 7:36 AM by Tyler Dickinson

September 9, 2019


Work Completed Last Week:

The underground contractor continued the installation of fire hydrants, water valves, and private water service connections last week. To date, over 70% of the private water services have been completed. The contractor also completed storm sewer repairs along Woodland Dr. over the weekend.

Anticipated Schedule for This Week:

T
he underground contractor will continue with the new water service connections along Oakwood Pl. and Hawthorne Ln. During these connections, short term water disruptions will be required so the homes can be connected to the new main. The contractor will also be connecting the new water mains to the existing mains at Woodbine Ct./North Ave. (Tuesday), Oakwood Pl./North Ave. (Wednesday), and Crabtree Ln. / Woodland Dr. (Thursday) which will require water impacts for those in the area during the work. 

The contractor is expected to be completed in the next 2-3 weeks with the required water main project. Once this project is completed, the road rehabilitation project will begin.  

Percentage Complete: 72%

Neighborhood Impacts:

Construction operations will require water main impacts as well as daily lane closures during working hours which may result in delays to
local vehicular traffic. Caution shall be practiced through the construction work zone, and the Village asks that residents be alert for workers and construction equipment.


The Village appreciates your patience while we complete this improvement. If you have any questions or need additional information, please contact the Village of Deerfield Engineering Department at 847-317-2490.

Please be advised that the information communicated here is a forecast of proposed operations which may change due to contractor availability and/or weather conditions.


Sep 03

Woodland WM Project Update - September 3

Posted on September 3, 2019 at 7:38 AM by Tyler Dickinson

September 3, 2019

Work Completed Last Week:

The underground contractor continued the installation of fire hydrants, water valves, and private water service connections. The underground contractor has completed all underground improvements on Woodland Dr. from Wilmot Rd. to Stratford Rd.

Anticipated Schedule for This Week:

The underground contractor will continue with the new water service connections along Woodbine Ct. and Oakwood Pl. During these connections, short term water disruptions will be required so the homes can be connected to the new main. The contractor will also continue testing the new water main in preparation for the new services to be hooked up. 

Percentage Complete: 64%

Neighborhood Impacts:

Construction operations will necessitate daily lane closures during working hours which may result in delays to
local vehicular traffic. Caution shall be practiced through the construction work zone, and the Village asks that residents be alert for workers and construction equipment.


The Village appreciates your patience while we complete this improvement. If you have any questions or need additional information, please contact the Village of Deerfield Engineering Department at 847-317-2490.

Please be advised that the information communicated here is a forecast of proposed operations which may change due to contractor availability and/or weather conditions.