2019 Woodland Watermain Project

Click here to view the complete project details including scope and locations.

Jun 23

Weekly Project Update - June 23

Posted on June 23, 2019 at 11:23 AM by Tyler Dickinson

Anticipated Schedule for Next Week:

RJ Underground will resume installation of new water main via directional drilling operations on Woodland Drive from Oakwood Place to Crabtree Lane.

RJ Underground will continue pot-holing existing utilities from Crabtree Lane to Stratford Road.

Percentage Complete: 11%

Neighborhood Impacts:

Construction operations will necessitate daily lane closures during working hours which may result in delays to local vehicular traffic. Caution shall be practiced through the construction work zone, and the Village asks that residents be alert for workers and construction equipment.

The Village appreciates your effort in helping to complete this improvement. If you have any questions or require special assistance during construction, please contact the Village of Deerfield Engineering Department at 847-317-2490 and request to speak with someone regarding the Woodland Subdivision Water Main Project.

Please be advised that the information communicated here is a forecast of proposed operations which may change due to contractor availability and/or weather conditions.




Jun 07

Woodland WM Project Update - June 7

Posted on June 7, 2019 at 3:51 PM by Tyler Dickinson

Work Completed:

The contractor installed temporary erosion control measures and temporary tree protection fence on Woodland Drive from Wilmot Road to Hawthorne Place.

Underground crews started directional drilling operations of the new water main on Woodland Drive from Oakwood Place to Wilmot Road.


Issues Encountered:
No issues to note.

Anticipated Schedule for Next Week:

The boring contractor will continue and finish the installation of new water main via directional drilling operations from Crabtree Lane to Wilmot Road.

Percentage Complete: 7%

Neighborhood Impacts:

Construction operations will require daily lane closures during working hours, which may result in delays to local vehicular traffic. Please be cautious through the construction work zone, and residents shall be alert for workers and construction equipment. We will continue to provide notice to affected residents and stakeholders as construction progresses.

The Village appreciates your effort in helping to complete this improvement. If you have any questions or require special assistance during construction, please contact the Village of Deerfield Engineering Department at 847-317-2490 and request to speak with someone regarding the Woodland Subdivision Water Main Project.





Jun 01

Update for Week of 6/3: Water Main Work Begins

Posted on June 1, 2019 at 9:28 AM by John Guccione

Water main work will begin work on Monday, June 3rd. This work will include excavating in various locations on Woodland Drive for bore pits and for "vertical utility locates" on existing gas lines and other services. Directional boring of water main on Woodland Drive will be the initial focus of underground work. Once Woodland Drive's water main installation is completed, then the contractor will shift their focus onto the side streets. Pipes and various other materials will be delivered through-out the week and will be stored within the project limits in the parkway areas.

Televising of sanitary service lines has been accomplished for lines which will be crossed during our directional boring operations.  Previous and post televising of the sanitary services lines are performed to verify that no service lines are impacted during the project.

Televising of storm sewers may also proceed this week through the project limits.