2019 Street Rehab Project

Click here to view the complete project details including scope and locations.

Sep 18

Paving Begins Tomorrow on Meadow (Road Closed), Wilmot Road and Berkeley Court

Posted on September 18, 2019 at 4:36 PM by John Guccione

Paving will take place on Thursday (9/19) and Friday (9/20) at various locations in the Village of Deerfield.

Paving schedule provided below:

MEADOW LANE Paving Thursday 9:30 a.m. to 1 p.m. ROAD CLOSED
Paving will begin at 9:30 a.m. on Meadow Lane which will result in the complete closure of Meadow Lane from 9:30 a.m. to 1 p.m.   The dead end and narrow roadway at this location dictate the need to pave Meadow Lane using the full width of the roadway.

WILMOT ROAD:  Paving Thursday afternoon after completion of Meadow Lane.

BERKELEY  COURT:  Paving Thursday afternoon and Friday morning if needed. 

ROSEMARY TERRACE:   Paving on Friday.

During tomorrow’s operation the contractor will place 1 to 2 inches of hot mix asphalt leveling binder. Once this layer of asphalt has time to cool, traffic will be permitted to travel across it (1-2 hours after placement).

Upon completion of tomorrow’s paving operation, this will leave a 2-inch gap at the curb which is accessible by vehicles (drive slowly through driveway approaches). The contractor will return at a later date to place the remaining 2-inch surface course, as additional work will be required prior to placement of surface course. Additional notice will be provided prior to surface course paving, as surface paving will also result in a daytime closure of Meadow Lane.

Paving operations will include heavy truck traffic and will present major delays to through traffic. During this time and if possible, please avoid the construction operations and utilize adjacent roadways. All driveways will be accessible at the completion of the work day. 

fresh-oil

Please be aware that signs stating “Fresh Oil” may be observed throughout the time period when asphalt paving will occur. The use of fresh oil helps different layers of asphalt to adhere to one another providing a longer lasting final product. Residents should be mindful of driving through fresh oil. If a detour is not in place and motorists must drive through fresh oil, please drive slowly. Driving at higher speeds through fresh oil may cause the material to adhere to the undercarriage and/or fenders of the car, which can be difficult and costly to remove.


Sep 16

Update for Week of 9/16

Posted on September 16, 2019 at 7:38 AM by John Guccione

Berkeley Court:  ACTIVE  80% complete 
Pavement grinding was completed last Friday.  Paving is scheduled for this Thursday. On Thursday 9/19/2019 the contractor will place the first layer of (leveling) asphalt. Paving operations will result in delayed access to the roadway. Physical notices will be distributed that provide additional info. Once paving is completed, the contractor will spend 1-3 week preparing all locations for final surface paving.

Meadow Lane: ACTIVE  80% complete 
Pavement grinding was completed last Friday.  Paving is scheduled for this Friday. On Friday 9/20/2019 the contractor will place the first layer of (leveling) asphalt. Paving operations will result in delayed access to the roadway. Physical notices will be distributed that provide additional info. Once paving is completed, the contractor will spend 1-3 week preparing all locations for final surface paving.

Wilmot Road (Greenwood to North Ave) ACTIVE  80% complete 
Pavement grinding was completed this past Saturday.  Paving is scheduled for this Wednesday. On Wednesday 9/18/19 the contractor will place the first layer of (leveling) asphalt. Paving operations will result in delayed access to the roadway. Physical notices will be distributed that provide additional info. Once paving is completed, the contractor will spend 1-3 week preparing all locations for final surface paving.

Rosemary Terrace:
 ACTIVE 75% complete 
Pavement grinding was completed this past Saturday. On Wednesday an additional round of concrete removal and replacement will take place in preparation for paving on Friday. On Friday 9/20/2019 the contractor will place the first layer of (leveling) asphalt. Paving operations will result in delayed access to the roadway. Physical notices will be distributed that provide additional info. Once paving is completed, the contractor will spend 1-3 week preparing all locations for final surface paving.

Birchwood Ave: AWAITING SURFACE PAVING 90% complete 
Adjustments to underground structures will take place this week in preparation for surface course paving tentatively set for the week of September 23rd.

WarringtonAWAITING SURFACE PAVING 90% complete 
Driveway restoration will take place this week north of Warwick., Adjustments to underground structures will also take place this week in preparation for surface course paving the week of September 23rd.  Sod has been placed south of Warwick. Sod to be placed north of Warwick next week, pending completion of driveway approach restorations that will take place later this week.

Castlewood, Cranshire, Montgomery, Chatham, Peartree & Village Green: 99% complete
Brick paver restoration began this past Saturday and will continue through the week. Restoration of parkway areas has been completed. Punch list items remain.

***PLEASE NOTE THAT THIS IS A FORECAST OF THE OPERATIONS PLANNED FOR THE WEEK.   DATES ARE SUBJECT TO CHANGE, DEPENDENT UPON WEATHER & CONTRACTOR AVAILABILITY.

Sep 09

Update for Week of 9/9

Posted on September 9, 2019 at 8:48 AM by John Guccione

Berkeley Court:  ACTIVE  60% complete 
The depressed concrete curb will be poured on the south side of the street on Monday, September 9th. On Thursday afternoon, the contractor will return to grind the 2" surface to reveal the subsurface. Once the subsurface is revealed, patching of any subsurface failures will take place previous to placing the first layer of asphalt which is tentatively planned for September 19th.

Meadow Lane: ACTIVE  60% complete 
On Thursday morning, the contractor will return to grind the 2" surface to reveal the subsurface. Once the subsurface is revealed, patching of any subsurface failures will take place previous to placing the first layer of asphalt which is tentatively planned for September 19th.

Wilmot Road (Greenwood to North Ave)    ACTIVE 60% complete 
Two small drainage structures will be replaced on Wednesday and will complete underground repairs on Wilmot.  A third (smaller) phase of concrete will be performed Monday & Tuesday. Surface pavement grinding (2" depth) will take place on Friday. Once the subsurface is revealed, patching of any subsurface failures will take place previous to placing the first layer of asphalt which is tentatively planned for September 20th.

Rosemary Terrace:
  Concrete removal and replacement will take place on Tuesday in relation to a slight widening of the roadway at Deerfield Road, to allow the installation of a turn lane. The contractor will return on September 16th to grind the surface pavement in preparation for resurfacing.

Birchwood Ave: AWAITING SURFACE PAVING 80% complete 
Adjustments to underground structures will take place this week in preparation for surface course paving tentatively set for the week of September 23rd.

WarringtonAWAITING SURFACE PAVING 80% complete 
Driveway restoration will take place this week north of Warwick., Adjustments to underground structures will also take place this week in preparation for surface course paving the week of September 23rd.  Sod has been placed south of Warwick. Sod to be placed north of Warwick next week, pending completion of driveway approach restorations that will take place later this week.

Castlewood, Cranshire, Montgomery, Chatham, Peartree & Village Green: 99% complete
Restoration of parkway areas has been completed. Punch list items remain.