Blog module icon

2019 Street Rehab Project

Click here to view the complete project details including scope and locations.

Jun 13

Warrington Road: Planned Water Shut Down on Friday June 14th

Posted on June 13, 2019 at 2:26 PM by John Guccione

6-14-19-WARRINGTON-hydrant-replacementsThere will be a planned water main shutdown on Warrington Road on Friday, June 14th from 9 a.m. through 3 p.m.. The limits of these impacts will be on Warrington Road from Warwick Road to Westgate Road.   Impacted residents were notified on Wednesday, June 12th via water department door hangers.

This interruption of water service is required in order to install the large diameter storm sewer on Warrington Road.  During this operation the contractor will also relocate three of the remaining six fire hydrants which remain to be relocated behind the sidewalk.


Jun 07

Update for Week of 6/10: Work Continues on Warrington, Cranshire, Montgomery plus Meadow Lane

Posted on June 7, 2019 at 4:27 PM by Tyler Dickinson

Warrington Road Storm Sewer
The contractor continued installation of the large diameter storm sewer this week and will continue next week. Beginning Wednesday, after the Walden School is out for the summer, the contractor will begin work between Essex Ct and Warwick Rd which will require a closure of this section of road.  Part of this work will require the relocation of water main along Warrington Rd which will result in a water impact to nearby residents. All impacted residents will be notified prior to this work taking place. Once this work is completed to Warwick, the contractor will begin concrete removals and replacements between Warwick and Woodvale.


Castlewood, Cranshire, Montgomery, Chatham, Pear Tree & Village Green: 
This week, the contractor completed the remainder of the new curb installation. All impacted driveways will be reinstated by the end of the day Friday and will be maintained until the contractor is ready to install the new sidewalk. The remaining sidewalk is anticipated to be installed next week. Residents whose driveways will be impacted will receive additional notification next week once a date has been determined by the contractor. Currently, it is anticipated that pavement removal will begin in the next 1-2 weeks with paving to follow the week of June 17.

Meadow Lane
The contractor was not able to begin curb removals on the south side of the road as planned this week. Once a date has been established by the contractor, notices will be hand delivered to the residents on Meadow Lane. Updates will also be communicated via the message board near Stratford Rd.

Please be advised that the information communicated here is a forecast of proposed operations which may change due to contractor availability and/or weather conditions.



Jun 01

Update for Week of 6/3: Work Continues on Warrington, Cranshire, Montgomery plus Meadow Lane

Posted on June 1, 2019 at 10:48 AM by John Guccione

PLEASE READ THE ENTIRE NOTICE, as it provides status and maps for various locations.

Warrington Road  
(Water shut down on Monday, June 3rd)

Underground work continues with a planned interruption of water service on Monday June 3rd from 10 am through 2 pm. This water shut down is the result of a water valve which requires replacement (indicated by red X on map below). Residents to be impacted by Monday's water shut down are highlighted on the map below and were notified on Saturday June 1st using water department "Door Hangers".   Storm sewer work will continue through the week.

VALVE-replace-6-3-2019

Castlewood, Cranshire, Montgomery, Chatam, Pear Tree & Village Green: 
(Driveway Access Impacts on Monday, June 3rd)

On Monday, the contractor will continue to remove and replace curbs and sidewalks. This work will impact driveway access beginning on Monday at the locations listed below. Impacted residents were notified on Friday, May 31st by way of physical notices posted at their properties.

  • Montgomery Drive (entire west side)
  • Cranshire Court (entire north side)
  • Chatham Court  (spot repairs to areas marked with pink paint)
  • Peartree Road (spot repairs to areas marked with pink paint)
  • Village Green (spot repairs to areas marked with pink paint)
400-CASTLEWOOD-3rd-PHASE

Meadow Lane
(Driveway Access Impacts on Tuesday, June 4th)

On Tuesday, the contractor will begin removing and replacing curbs on the south side of Meadow Lane. This work will impact driveway access beginning on Tuesday. Impacted residents were notified on Saturday June 1st by way of physical notices posted at their properties.

800-MEADOW-concrete-PH1