The original item was published from November 3, 2019 11:52 AM to November 3, 2019 12:06 PM
11/3/2019
PAVING UPDATE
As you are aware, the contractor was not able to pave the final layer of asphalt last week as planned due to the unexpected weather. However, the final
layer of paving on Greenwood Ave. will take place tomorrow, Monday, November 4,
2019. The contractor has been approved for an
early start time to ensure that they are able to complete this work in one day.
Also, in an effort to minimize issues with the mandatory priming of the roadway
with fresh oil (see reverse side for more info), the contractor will apply the prime
coat beginning at 5 a.m. on Monday morning. An early application helps in
reducing impacts to the traveling vehicles.
Paving
operations will include heavy truck traffic and will present major delays to
through traffic. During
this time and if possible, please avoid the construction operations and utilize
adjacent roadways. During paving operations, homeowners
will have access to their property at all times via their driveway. However,
due to limited space, access to driveways may be impacted while paving
operations are in the vicinity. All driveways will be
accessible at the completion of the work day.
The
contractor will work to ensure that daily traffic is minimally impacted by utilizing
traffic flaggers. Please be mindful and obey these flaggers if traveling
through the work area.
The
Village appreciates your effort in helping to complete this improvement. If you
have any questions or need additional information, please visit the Village
website’s project blog or contact the Village of Deerfield Engineering
Department at 847-317-2490 and
request to speak with someone regarding the Project.
The original item was published from November 3, 2019 11:52 AM to November 3, 2019 12:04 PM
11/3/2019
PAVING UPDATE
This is notice that the final
layer of paving on Greenwood Ave. will take place tomorrow, Monday, November 4,
2019. The contractor has been approved for an
early start time to ensure that they are able to complete this work in one day.
Also, in an effort to minimize issues with the mandatory priming of the roadway
with fresh oil (see reverse side for more info), the contractor will apply the prime
coat beginning at 5 a.m. on Monday morning. An early application helps in
reducing impacts to the traveling vehicles.
Paving
operations will include heavy truck traffic and will present major delays to
through traffic. During
this time and if possible, please avoid the construction operations and utilize
adjacent roadways. During paving operations, homeowners
will have access to their property at all times via their driveway. However,
due to limited space, access to driveways may be impacted while paving
operations are in the vicinity. All driveways will be
accessible at the completion of the work day.
The
contractor will work to ensure that daily traffic is minimally impacted by utilizing
traffic flaggers. Please be mindful and obey these flaggers if traveling
through the work area.
The
Village appreciates your effort in helping to complete this improvement. If you
have any questions or need additional information, please visit the Village
website’s project blog or contact the Village of Deerfield Engineering
Department at 847-317-2490 and
request to speak with someone regarding the Project.
The original item was published from October 28, 2019 9:27 AM to October 28, 2019 9:28 AM
October 28, 2019
Work Completed Last Week:
The contractor patched and paved the first layer of asphalt on Greenwood, west of Chestnut St. last week. They also began removal and replacement of driveways at various locations.
Anticipated Schedule for upcoming weeks:
The contractor will continue to prepare the roadway for final paving which is anticipated to take place this week. Additional notification will be distributed prior to final paving. Once the roadway has been paved, the contractor will install the final pavement striping. The contractor will also continue with driveway and parkway restoration throughout the week.
This project has a contract completion date of October 31, 2019.
Percentage Complete: 73%
Neighborhood Impacts:
At times, vehicles will not be able to pass the contractor’s work operations which may result in delays to local traffic. Caution should be practiced through the construction work zone and residents must be alert for workers and construction equipment.
The Village appreciates your patience while we complete this improvement. If you have any questions or need additional information, please contact the Village of Deerfield Engineering Department at 847-317-2490.
Please be advised that the information communicated here is a forecast of proposed operations which may change due to contractor availability and/or weather conditions.