2017 Brierhill Road Infrastructure Project

The original category was published from February 22, 2017 11:15 AM to February 22, 2017 11:20 AM

Nov 18

[ARCHIVED] Update for week of November 18

The original item was published from November 18, 2019 7:12 AM to November 18, 2019 7:14 AM

In addition to the items noted below, pavement markings and minor punch list items remain at all locations.
_______________________
Berkeley Court:  
ACTIVE  99% complete 

Paving completed on Friday 11/8. Minor parkway restoration remains.

Birchwood Ave.:   100% complete

Castlewood Ln., Cranshire, Chatham, Peartree & Village Green: 100% complete


Meadow Lane: ACTIVE  99% complete 
Driveway restoration remains. 

Rosemary Terrace: 
ACTIVE 99% complete 
Minor parkway restoration remains. Placement of permanent pavement marking near Rosemary and Deerfield Road to be completed as weather permits.

Warrington Road ACTIVE 95% complete 
Mainline paving completed on Saturday 11/9. The paving contractor anticipates completing the remaining final paving near intersections this week as weather permits. 

Wilmot Road (Greenwood to North Ave): ACTIVE  99% complete 

Minor parkway restoration remains.

Woodland SubdivisionACTIVE 90% complete 
Final paving taking place today. Contractor will return for driveway restoration, minor parkway restoration, and pavement markings as weather permits. 
Nov 18

[ARCHIVED] Update for week of November 18

The original item was published from November 18, 2019 7:12 AM to November 18, 2019 7:14 AM

In addition to the items noted below, pavement markings and minor punch list items remain at all locations.
_______________________
Berkeley Court:  
ACTIVE  99% complete 

Paving completed on Friday 11/8. Minor parkway restoration remains.

Birchwood Ave.:   100% complete

Castlewood Ln., Cranshire, Chatham, Peartree & Village Green: 100% complete


Meadow Lane: ACTIVE  99% complete 
Driveway restoration remains. 

Rosemary Terrace: 
ACTIVE 99% complete 
Minor parkway restoration remains. Placement of permanent pavement marking near Rosemary and Deerfield Road to be completed as weather permits.

Warrington Road ACTIVE 95% complete 
Mainline paving completed on Saturday 11/9. The paving contractor anticipates completing the remaining final paving near intersections this week as weather permits. 

Wilmot Road (Greenwood to North Ave): ACTIVE  99% complete 

Minor parkway restoration remains.

Woodland SubdivisionACTIVE 90% complete 
Final paving taking place today. Contractor will return for driveway restoration, minor parkway restoration, and pavement markings as weather permits. 
Nov 18

[ARCHIVED] Update for week of November 18

The original item was published from November 18, 2019 7:12 AM to November 18, 2019 7:14 AM

In addition to the items noted below, pavement markings and minor punch list items remain at all locations.
_______________________
Berkeley Court:  
ACTIVE  99% complete 

Paving completed on Friday 11/8. Minor parkway restoration remains.

Birchwood Ave.:   100% complete

Castlewood Ln., Cranshire, Chatham, Peartree & Village Green: 100% complete


Meadow Lane: ACTIVE  99% complete 
Driveway restoration remains. 

Rosemary Terrace: 
ACTIVE 99% complete 
Minor parkway restoration remains. Placement of permanent pavement marking near Rosemary and Deerfield Road to be completed as weather permits.

Warrington Road ACTIVE 95% complete 
Mainline paving completed on Saturday 11/9. The paving contractor anticipates completing the remaining final paving near intersections this week as weather permits. 

Wilmot Road (Greenwood to North Ave): ACTIVE  99% complete 

Minor parkway restoration remains.

Woodland SubdivisionACTIVE 90% complete 
Final paving taking place today. Contractor will return for driveway restoration, minor parkway restoration, and pavement markings as weather permits.