May 27

Construction Update for week of 5/26/2020

Posted on May 27, 2020 at 10:56 AM by John Guccione

The below update provides a forecast of construction operations planned for the week of May 26, 2020. Please note that this forecast is subject to change due to weather.

PROJECT LOCATIONS LISTED IN ALPHABETICAL ORDER

Dartmouth Ave 
(Wilmot To Mallard.Including Pembroke and Circle Courts
Beginning on Thursday, May 28, 2020 and continuing through the end of the week, pavement grinding and subbase preparation will begin within the project limits. During this operation, the contractor will be removing the entire roadway pavement.
ORANGE highlighted area  
DARTMOUTH-pavement-removal
Pavement grinding and removal operations will include heavy truck traffic and may result in impacts to driveways while the pavement is being removed directly in front of a driveway. However, once grinding/removal is completed, the contractor will install stone access ramps that will allow access to all driveways. These ramps will remain in place until the following week’s pavement operations. 

GRINDING-OPERATION

Knollwood Rd (Warwick to Margate) plus Westgate
Project completed.   Only punch list items remain.  

Knollwood Rd 
(Margate to Kingston) plus Margate Terrace 
Project completed.   Only punch list items remain.  

Linden Ave (Stratford to Chestnut)
Underground work at this location was so minimal, that it was completed on May 26, 2020 (due to contractor availability).  Only minor adjustments to underground structures remain and will be performed previous to pavement removal.

Curb removal and replacement is planned along the northern portion of Linden Ave for next Thursday and Friday.   Upon completing the north side curb, the contractor will return the following week to remove and replace the south side.  Additional notice will proceed any driveway access impacts.

CORONAVIRUS NOTICE
The Village’s infrastructure construction projects fit under an exemption per the Governor’s Stay at Home order. Outdoor activities, like construction projects, generally will provide for good social distancing that poses little risk of transmission, but it still is important to ensure the ability to wash or sanitize hands and take other precautions. Village and contractor personnel will continue to practice safe social distancing and sanitation efforts during the construction.

If you have any questions or require special assistance during construction, please contact the Village of Deerfield Engineering Department at 
847-317-2490 and request to speak with someone regarding the 2020 Street Rehab Project.

May 14

Dartmouth Curb Pour Delayed Until Monday, May 18

Posted on May 14, 2020 at 6:42 PM by John Guccione


Dartmouth Lane
Late word from the contractor is that curb placement is delayed until Monday, May 18 for the south side of Dartmouth Lane and Kenmore Ave (north of Hackberry). Therefore, the stone access approaches will remain in place until 7:30 AM on Monday morning. 

Knollwood Road
Paving will take place on Friday, May 15 at 7:30 AM as previously communicated.
May 14

WEATHER DELAY- Dartmouth Curb & Knollwood Paving Now Planned for Friday

Posted on May 14, 2020 at 11:43 AM by John Guccione

The below update provides revised dates due to today's weather delays.

PROJECT LOCATIONS LISTED IN ALPHABETICAL ORDER

Dartmouth Ave 
(Wilmot Rd. To Pine St.Including Pembroke and Circle Courts
Today's curb pour is delayed due to rain.  All temporary driveways will remain in place until tomorrow morning at 7:30am.  Curb pour is moved to Friday for the entire south side of Dartmouth and Kenmore.
ORANGE highlighted area    Curb pour moved to Friday due to weather.
PINK highlighted =  Curb pour moved to Friday due to weather.
Green highlighted area Access restored.
revised-Dartmouth-south-sidewalk copy
Dartmouth Ave (Pine to Mallard)
Extended limits: Removal underway today
 curb pour planned for Monday, May 18. 
DARTMOUTH-east copy

Road-Fabrics-PAVINGKnollwood Rd (Warwick to Margate) plus Westgate
Paving was not possible on Wednesday due to paving contractor's delayed arrival on Wednesday.  Paving canceled for Thursday due to rain. "PAVING moved to Friday due to weather".

Knollwood Rd 
(Margate to Kingston) plus Margate Terrace 
"Paving Completed" 


During paving operations, pedestrian access will remain available by sidewalk. Due to these complete road closures, we ask residents who require frequent vehicular movement in or out of your home (between the hours indicated above) to relocate their vehicles outside of this operations limits. Please note that the contractor will halt operations for any emergency vehicles. Paving operations will include heavy truck traffic in the area. During this time and if possible, please avoid the construction operations and utilize adjacent roadways.  All driveways will be accessible at the completion of the work day.


CORONAVIRUS NOTICE
The Village’s infrastructure construction projects fit under an exemption per the Governor’s Stay at Home order. Outdoor activities, like construction projects, generally will provide for good social distancing that poses little risk of transmission, but it still is important to ensure the ability to wash or sanitize hands and take other precautions. Village and contractor personnel will continue to practice safe social distancing and sanitation efforts during the construction.

If you have any questions or require special assistance during construction, please contact the Village of Deerfield Engineering Department at 
847-317-2490 and request to speak with someone regarding the 2020 Street Rehab Project.