Aug 31

Update for Week of 8/31/2020

Posted on August 31, 2020 at 8:22 AM by John Guccione

The below update provides a forecast of construction operations planned for the week of August 31, 2020.  Please note that this forecast is subject to change due to weather and contractor availability.

ACTIVE LOCATIONS

Kenton Rd (Warwick to Deerfield Rd)  
Pavement removal begins on Monday, August 31 and will continue through the week on Kenton Rd. This work will include heavy truck traffic and will result in access impacts to residential driveways during the day. If vehicles are needed during the day, residents are asked to relocate their vehicles to adjacent streets prior to 7:30am each day. The contractor will install stone access ramps that will allow access to the roadway, and to all driveways at the end of each day.

WM-175Starting on Tuesday, September 1, Waste Management will begin EARLY trash collection on Kenton Road (Deerfield Road to Woodvale Avenue) starting at 6:00 a.m.

The Village recommends having your containers out the night before to ensure they are accessible for a 6:00 a.m. collection. This change is in an effort to ensure an unobstructed weekly trash collection while the nearby Kenton Road construction project is active. The Village would like to thank you for your cooperation while construction takes place.

COMPLETED LOCATIONS LISTED IN ALPHA ORDER

Dartmouth Ave 
(Wilmot to Mallard.Including Pembroke and Circle Courts
Project complete. Patch at Circle Court plus review and 2nd wave of parkway restoration will be completed before the end of the construction season.

Hillside Ave (Hazel to Somerset)
Location  completed.  Punch list items remain.

Knollwood Rd (Warwick to Margate) plus Westgate
Location  completed.  Punch list items remain.

Knollwood Rd 
(Margate to Kingston) plus Margate Terrace 
Location  completed.  Punch list items remain.

Linden Ave (Stratford to Chestnut)
Location  completed.  Punch list items remain.

If you have any questions or require special assistance during construction, please contact the Village of Deerfield Engineering Department at 
847-317-2490 and request to speak with someone regarding the 2020 Street Rehab Project.

Aug 03

Construction Update for Week of 8/3

Posted on August 3, 2020 at 12:44 PM by John Guccione

The below update provides a forecast of construction operations planned for the week of August 3.  Please note that this forecast is subject to change due to weather and contractor availability.

PROJECT LOCATIONS LISTED IN ALPHABETICAL ORDER

Dartmouth Ave 
(Wilmot to Mallard.Including Pembroke and Circle Courts
Paving completed. Punch list items remain which include parkway restoration and minimal concrete repairs.  Please note that the water main break at Dartmouth and Circle Court was not relative to construction.  However, the contractor will perform pavement repairs in the next 2-3 weeks.

Hillside Ave (Hazel to Somerset)
Paving completed. Sod will be placed this week. The contractor will be responsible for water for 2 weeks. 

Kenton Rd (Warwick to Deerfield Rd)  
**
NEW LOCATION**
Removal of sidewalk and curb will take place along the west side of Kenton later this week. Additional notice will be provided to impacted residents via physical notification prior to impacts.

Knollwood Rd (Warwick to Margate) plus Westgate
Project completed.   Only punch list items remain.  

Knollwood Rd 
(Margate to Kingston) plus Margate Terrace 
Project completed.   Only punch list items remain.  

Linden Ave (Stratford to Chestnut)
Paving completed. Sod will be placed this week. The contractor will be responsible for water for 2 weeks. 

If you have any questions or require special assistance during construction, please contact the Village of Deerfield Engineering Department at 
847-317-2490 and request to speak with someone regarding the 2020 Street Rehab Project.

Jul 13

Construction Update for week of 7/13 - Paving This Week

Posted on July 13, 2020 at 2:19 PM by Tyler Dickinson

_2020_KENTON-CLOSURESThe below update provides a forecast of construction operations planned for the week of July 13.  Please note that this forecast is subject to change due to weather and contractor availability.

PROJECT LOCATIONS LISTED IN ALPHABETICAL ORDER

Dartmouth Ave 
(Wilmot to Mallard.Including Pembroke and Circle Courts
Final surface paving is planned for this Friday, July 17th.   See notes regarding paving operations and prime coat placement at the end of this notice.

Hillside Ave (Hazel to Somerset)
Final surface paving is planned for this Thursday, July 16th. See notes regarding paving operations and prime coat placement at the end of this notice.

Kenton Rd (Warwick to Deerfield Rd) 
**
NEW LOCATION**
Underground work will begin on Tuesday, July 14th which will result in closures Kenton Road, on sections where the contractor is performing repairs.  Please use alternative roads and avoid accessing sections where "Road Closed to Through Traffic" are posted.

Knollwood Rd (Warwick to Margate) plus Westgate
Project completed.   Only punch list items remain.  

Knollwood Rd 
(Margate to Kingston) plus Margate Terrace 
Project completed.   Only punch list items remain.  

Linden Ave (Stratford to Chestnut)
Final surface paving is planned for this Thursday, June 16th.   


fresh-oilPlease be aware that signs stating “Fresh Oil” may be observed throughout the time period when asphalt paving will occur. The use of fresh oil helps different layers of asphalt to adhere to one another providing a longer lasting final product. Residents should be mindful of driving through fresh oil. If a detour is not in place and motorists must drive through fresh oil, please drive slowly. Driving at higher speeds through fresh oil may cause the material to adhere to the undercarriage and/or fenders of the car, which can be difficult and costly to remove.

VEHICULAR ACCESS DURING PAVING WILL BE LIMITED. This work will include heavy truck traffic and will result in impacts to driveways during the day. If vehicles are needed during the day, residents are asked to relocate their vehicles to adjacent streets prior to 7:30 am each day.  Access will be restored at the end of paving.

If you have any questions or require special assistance during construction, please contact the Village of Deerfield Engineering Department at 
847-317-2490 and request to speak with someone regarding the 2020 Street Rehab Project.