Q: When is a building permit required?
A: A building permit is required for any commercial and residential construction projects that entail an addition or remodeling of the existing conditions. Also fences, roofs, decks, porches, patios garages and sheds all require a building permit. If in doubt please contact the Building Department at 847-719-7484.
You will not need a permit if you are making only cosmetic changes to your home, i.e. installing new cabinets, changing a fixture. But if you are doing any electrical or plumbing work, a permit is required.
back to top 
Q: How do I obtain a building permit?
A: A permit can be obtained by visiting the Village Hall at 850 Waukegan Road or online applications are available.
General permit submission information is available
here.
back to top 
Q: How much does a building permit cost?
A: The cost of the permit is generally based on the cost of the job; however there are other costs that may be included depending on the type of project which is planned.
Click
here for a list of fees.
back to top 
Q: How do I check on the status of a building permit application that I have submitted?
A: When you submit your building permit, you may be given an approximate plan review time. This review time will vary depending on the size of your project, the time of year, review of the drainage and grading plans by the Village Engineering Department as well as how many other permit applications are in line ahead of yours. Once plan review has begun on your permit application, the homeowner and contractor will be contacted if the plan reviewer has any questions or problems, or any additional information is needed. Once your plans and permits have been approved, the homeowner and/or contractor will be notified that they are ready to be picked up, and of the total permit cost due. Plans and permit fees may be paid at the Village Hall. You may call the Building Department and ask what the status of your permit review is, but please keep in mind the approximate plan review time you were told when you submitted your plans was only an estimate on the departments work load at the time and unforeseen projects throughout the Village of Deerfield may have taken priority.
Please keep in mind that the homeowner and the contractor will be called if there are questions or problems and will be called when the plans and permit are ready for pick up.
back to top 
Q: When do I need inspections and who do I call?
A: Chances are if you have a permit you will need something inspected, the permit application has a list of when inspections should be call for and prior to certain stages of the project items need to be checked for code compliance. To schedule an inspection with a building inspector or plumbing inspector, call the Building Department at (847) 719-7484. Engineering and site development inspections and inspections that take place within the right-of-way are scheduled through the Engineering Department at (847) 719-2490. Fire Department inspections are scheduled through the appropriate fire protection district.
back to top 
Q: What hours is construction is allowed?
A: There are hours during which construction may occur are: Monday through Friday – 7:30 a.m. to 7:00 p.m. Saturday – 8:30 a.m. to 5:00 p.m. No construction is allowed to take place on Sundays or on the following holidays: New Year’s Day (Jan. 1), the day on which Memorial Day is observed, the Fourth of July, Labor Day, Thanksgiving Day and Christmas Day (December 25).
If construction is taking place outside the permitted times, call the Deerfield Police non-emergency phone number at (847) 945-8636.
back to top 
Q: How can I obtain a copy of my plat of survey?
A: The Community Development Department keeps files on every address in Deerfield. We have plats of survey for some properties, but not all of them. You may call the Community Development Department at (847) 719-7484 and ask a staff member to look in your home’s file. If we have a plat of survey on file, the homeowner may have a copy at no charge. We can only release copies of plats of survey to a homeowner – not to a real estate agent, potential buyer, contractor or anyone else.
back to top 
Q: How do I determine zoning on a property?
A: To find out the zoning district in which your property is located, go to the
Zoning Map and locate your property on the color coded map.
back to top 
Q: How do I determine the required setbacks from the property line for a certain property?
A: You must determine the zoning district for your property. To find out the zoning district in which your property is located, go to the
Zoning Map and locate your property on the color coded map. You should call the Community Development Department at (847) 719-7484 and ask a staff member for the setbacks on a property as setbacks and building lines vary by zoning district.
back to top 
Q: How can I determine if I can build a new house or add on to my existing house?
A: Due to the unique nature of the many and varied zoning restrictions applicable in all the listed Zoning Districts, the question as to whether an addition or expansion of an existing home or development of any existing property is possible should be discussed with Community Development staff before entering into any contractual commitment.
Click here for additional information.
back to top 
Q: How do I obtain plans for my house?
A: The Community Development Department keeps files on every address in Deerfield. We may have plans for some houses, but not all of them. You may call the Community Development Department at (847) 719-7484 and ask a staff member to look in your home’s file. If we have paper house plans on file, the homeowner may request a copy at their expense. The Village does not have a large format copier and the plans will have to be sent out for copying at the homeowner’s expense. A note on floor plans: for security reasons we can only release copies of floor plans to a homeowner – not to a real estate agent, potential buyer, contractor or anyone else.
Sometimes we have house plans on microfiche. At this time, we are not able to make copies of plans on microfiche. Most companies no longer make copies from microfiche because the technology is outdated, and for the companies that still make these copies they are often expensive and the quality is very poor.
back to top 
Q: What if there is construction happening in my neighborhood and I have questions and concerns?
A: Construction can bring about many questions and concerns. Click
here to read about some common concerns.
back to top 
Q: What if my neighbor is doing construction, and I don’t think they have a permit?
A: When a building permit is issued, the contractor and the homeowner are informed they need to display the building permit in the home’s front window, on the construction fencing, or someplace visible from the street. The building permit is a yellow card that states “Building Permit” and contains the address, permit number and date of issue. The permit is good for one year from the date of issue. If you believe someone is working without a permit, you can call the Building Department at (847) 719-7484 to report it and an inspector look into the situation. Please keep in mind that no permit is needed for cosmetic work such as changing cabinets, countertops or fixtures.
back to top 
Q: What if I need a dumpster?
A: Dumpsters do not require a special permit. Dumpsters must be placed on private property, preferably in the driveway. Dumpsters may not be placed in the street or in the right-of-way.
back to top 
Q: What is the right-of-way?
A: The right-of-way is Village owned area that is also known as the parkway. Right-of-way extends 15 feet from the curb line on either side of the street. In order to dig in the right-of-way a deposit must be paid to the Village. The deposit ensures that the right-of-way will be restored.
back to top 
Q: How do I find out if my property is in a flood plain or flood zone?
A: To find out if your property is located in a flood plain or flood zone go to http://www.fema.gov/hazard/map/flood.shtm, click “find a flood map online.” Go to “product search by address,” select “public flood map,” type in your address, and click “product search.” Click “view” to view the flood map of your area. You can also contact the Village’s Engineering Department with flood plain questions.
back to top 
Q: What is the role of the Board of Zoning Appeals?
A: The Board of Zoning Appeals (BZA) holds public hearings on requests for variations and modifications to the Zoning Ordinance, which include variations from minimum lot requirements; bulk regulations; off-street parking and loading requirements; nonconformities; and modifications for fences and signs. The BZA has certain criteria that need to be met before a variation or modification can be granted. The BZA is a seven member Commission which meets on the 1st and 3rd Tuesdays of each month at 7:30 p.m. at the Village Hall. The Board of Trustees considers the BZA’s recommendation and makes a final decision. The staff liaison for the BZA is Clint Case, Code Enforcement Supervisor, who can be reached at (847) 719-7472.
back to top 
Q: What are the current public hearing fees?
A: The public hearing fee is $175 plus the cost of publishing the legal notice in the newspaper and any county recording fees for ordinances and other documents.
back to top 
Q: Where can residential open house and for sale signs be placed and when are they allowed?
A: Open house signs and Real Estate signs are permitted, however the open house signs are only allowed on Wednesdays between the hours of 9 a.m. to 1 p.m. and Sundays between the hours of 12 noon to 6 p.m.
back to top 
Q: Where can political signs be placed and when are they allowed?
A: Political signs are only allowed to be placed on private property. Time limits for political signs are requested to be no more than (30) days prior to an election and removed (7) days following an election.
back to top 