Brierhill Road Project Construction Update – 9/22/2017

 

Signage

Last week, the contractor completed the remainder of the punch list items including the installation of the new roadway signage. This signage, especially around the curves, will be evaluated by the Village and altered/removed as needed.


Paving

This morning, the Village confirmed with the paving contractor that they anticipate paving the final layer of asphalt next Sunday night (10/1) into Monday morning. This night work is in an effort to minimize any further impacts to residents and daily traffic. An additional notification with further information regarding this work will be sent out later in the week.

 

 

Please be advised that the information communicated here is a forecast of proposed operations, which may change due to contractor availability and/or weather conditions.