Jun 02

Construction Forecast for the week of 5/22/2017

Posted on June 2, 2017 at 3:12 PM by John Guccione

This construction forecast is for the week of May 22, 2017 and contains updates for Fair Oaks Avenue, Garand Drive and Pine Street locations.

Fair Oaks Ave Update:
Removal of the concrete sub-base will begin today. Following the removal of pavement the contractor will install aggregate sub-base. Pavement removal operations will likely pause during the week as rain is in the forecast. Pavement removal will proceed as weather permits.

Garand Drive Update: Underground storm sewer repairs will take place this week on Garand along with tree removal and tree preservation techniques such as root pruning, crown pruning and tree fencing installation.

Pine Street Update:  Paving of base course was completed last week. The contractor intends to return later this week to complete sod placement. Placement of asphalt surface course will take place in 2-3 weeks.