Jun 23

Construction Forecast for the week of 6/26/2017

Posted on June 23, 2017 at 2:41 PM by John Guccione

This construction forecast is for the week of June 26, 2017.

Garand Drive 
Underground sewer repairs and concrete curb and sidewalk installation has been completed on Garand Drive. Pavement removal could begin towards the middle of next week (weather permitting). Additional notice will follow prior to pavement removal. As pavement removal operations could present delayed access to residential driveways.

Wincanton Drive
Construction layout and utility locates have been completed in preparation for the upcoming construction project. Underground sewer work could begin as early as July 5th.

Pine Street
Sod placement is complete. The only remaining work at this location is the placement of asphalt surface pavement, which will take place in the next two months. 

Fair Oaks Avenue
Sod placement is complete. The only remaining work at this location is the placement of asphalt surface pavement, which will take place in the next two months. 

Continue Reading...

Jun 02

Early Start Approved for Saturday on Garand Dr. & Construction Forecast for the week of 6/5/2017

Posted on June 2, 2017 at 3:53 PM by John Guccione

This construction forecast is for the week of June 5, 2017.

Residents of Garand Drive: Take note that the Village has approved an early start that will allow the contractor to start at 7:30 a.m. this Saturday, June 3, to accelerate the project.

Garand Drive Construction Forecast
This week, the contractor completed curb placement along the north curb-line on Garand Drive. The contractor will begin work early on work on Saturday in order to complete excavation and preparation for the installation of sidewalk that will begin on Monday and Tuesday.

Pine Street Update
Sod placement is complete. Watering will continue over the next ten days. Any remaining concrete replacement be completed next week. The only remaining work at this location is the placement of asphalt surface pavement, which will take place in the next two months. 

Fair Oaks Avenue Update
Sod placement is complete. Watering will continue over the next ten days. Any remaining concrete replacement will be completed next week. The only remaining work at this location is the placement of asphalt surface pavement, which will take place in the next two months. 


Continue Reading...

Jun 02

Construction Forecast for the week of 5/22/2017

Posted on June 2, 2017 at 3:12 PM by John Guccione

This construction forecast is for the week of  May 22, 2017 and contains updates for Fair Oaks Avenue, Garand Drive and Pine Street locations.

Fair Oaks Ave Update: 
Removal of the concrete sub-base will begin today. Following the removal of pavement the contractor will install aggregate sub-base. Pavement removal operations will likely pause during the week as rain is in the forecast. Pavement removal will proceed as weather permits.

Garand Drive Update: Underground storm sewer repairs will take place this week on Garand along with tree removal and tree preservation techniques such as root pruning, crown pruning and tree fencing installation.

Pine Street Update:  Paving of base course was completed last week. The contractor intends to return later this week to complete sod placement. Placement of asphalt surface course will take place in 2-3 weeks.

Continue Reading...