2019 Street Rehabilitation Project

The Village of Deerfield is pleased to announce the execution of the 2019 Street Rehabilitation Project.  

A project-related public meeting was held on Wednesday, April 10, 2019, at 7 p.m. to allow for the flow of information and questions from residents. If you were unable to attend, watch the meeting below or view the presentation slides here



The Department of Public Works and Engineering has identified various locations to be included in this year’s project. Locations and scope of work per location is provided below:
2019-STREET-REHAB-MAP
2019-Locations

Stage I:  Underground Utility Work


Stage I includes storm sewer work as it relates to roadway drainage and minor water main repairs. The majority of construction will be performed in the roadway area with the exception of the replacement of storm sewer structures and/or fire hydrants within the parkway area. If you have existing appurtenances within the parkway or Village right-of-way (i.e. sprinkler system, electronic “invisible” dog fence, landscape features, special decorative rocks, special vegetative plantings), you should remove/relocate or store these items to avoid damage by construction activity. The Village will not repair or replace private appurtenances left within the parkway or Village right-of-way that are damaged during construction. 

Stage II:   Concrete Curb Removal/Replacement, Sidewalk Repair and Roadway Rehabilitation


Stage II will begin upon completion of the underground utility work. Work will be performed as follows:  

  • Removal and replacement of all deteriorated curbs and sidewalks
  • Removal of roadway pavement and placement of new bituminous asphalt pavement (Note: Reconstruction requires complete removal and replacement of the roadway, down to sub-base, while resurfacing requires the removal and replacement of only the top 2-4 inches of pavement.)                             
  • Repair of driveway sections and sidewalk impacted by construction  
During Stage II, the road will be closed to through traffic and driveways may be impacted while concrete curbs, driveway aprons and concrete sidewalk are being installed. Residents will be advised to park their vehicles on adjacent streets during construction hours (7:30 a.m. to 7:00 p.m.) or in front of their homes after construction hours. The Deerfield Police Department will be notified that residents will be parking in these areas during this stage of construction. 

Stage III:    Parkway Restoration

   
All parkway areas disturbed by construction activity will be restored. Construction is expected to be completed by November 16, 2019. However, due to the complex nature of the project and the unpredictability of the weather, some delays and disruptions may occur.  Additional construction notices will be provided as the project progresses.  If you are planning a special event, such as a wedding or large party, or have special needs, please contact the Engineering Department and we will do our best to accommodate you.
NOTIFY-ME
Moving forward, all future notifications will be provided using the Village email notification system. The Village will be sending out email notifications to those who have subscribed to receive them. Residents are able to subscribe to email notifications here.   

Please be advised that multiple email addresses may subscribe per household. Therefore, please be sure to add emails for all individuals that reside in or visit your property regularly.

The Village appreciates your effort in helping to complete this improvement. If you have any questions or require special assistance during construction as a result of a disability, please contact the Village of Deerfield Engineering Department at 847.317.2490 and request to speak with someone regarding the 2019 Street Rehabilitation Project. 

Please remember to drive and walk carefully through the construction zone.